PIR insulation
SOPREMA EFYOS BLUE A in renovation: checking beneath the roof covering
At a glance
On the roof being renovated, the old flashings were retained, but once the covering was opened up it turned out that the substrate had different levels from those in the documentation. The thickness of BLUE A must therefore be compared again with the height of the parapet. It is not worth cutting the entire delivery according to an outdated assumption. First, a measurement is needed and a decision on how the covering is to be terminated. In a renovation, the scope described as thermal insulation of a flat roof beneath the waterproofing requires an investigation of the old layers. The first difficult place to inspect is the termination of the thermal insulation at the parapet. It is not worth determining the thickness of EFYOS BLUE A solely on the basis of an old drawing. The measurement should cover the height of the parapet above the target covering surface, taking into account changes made during earlier works.

What has to be exposed before selection
On this basis, a parapet cross-section is produced with the levels of all layers. The purpose of the survey is to answer the question of whether the existing conditions allow the thermal layer to be accommodated and the waterproofing to be correctly terminated.
The right product and the scope of its data
Choosing EFYOS BLUE A for the assembly uncovered during the renovation requires identification of the entire board: the PIR core has aluminium 50 μm thick on both sides. For thermal comparison, the document states RD 4.50 m²K/W at 100 mm and 5.45 m²K/W at 120 mm, with a declared λD of 0.022 W/(m·K). CS(10/Y)120 and the product’s reaction to fire E are recorded separately. These are the data of the factory element with facings, not of the foam alone in any form. When ordering, enter the full name and edge finish. The straight-edge and profiled-edge variants may differ in the relationship between the external dimension and the coverage, which must be taken into account when planning the new layer under the covering.
An example versus the actual condition of the renovation
At the parapet, the height remaining above the planned covering is checked. A simplified example for EFYOS BLUE A can be set out as follows: available space 150 mm, remaining required layers 50 mm, space for insulation 100 mm. A 120 mm board variant would give 170 mm in total and would require changes to the levels. This is an illustration of the balance, without a recommendation for a cross-section for a specific roof or floor. In a real renovation, the levels must be measured and related to the parapet flashing. The availability of a thicker product does not remove the limitation arising from this termination.
The calculation presented for EFYOS BLUE A serves to organise the decision in advance. In an old building, the result must be confronted with the limitation: the height limit at the flashing. The property of the new board described as lambda 0.022 W/(m·K) does not remedy a shortfall elsewhere. On site, the level of the covering must be compared with the flashing drawing before the final scope of works is adopted. The check should be documented by a parapet cross-section with the levels of all layers. If it proves inconsistent with the assumption, the EFYOS BLUE A order must be adjusted before repetitive cutting begins.
Which scope of repair is justified
One measure under consideration is increasing the thickness of the board. A second may be refining the junction at the roof perimeter, depending on the result of the exploratory opening. With EFYOS BLUE A, both variants should take into account the location of the repair: the termination of the thermal insulation at the parapet. Before a decision is made, the possibility of using the entire available height for the insulation alone must be ruled out. The result of the inspection should be assessed by the designer of the roof section, who will link the repair to the remaining layers. Once agreed, a schedule of thicknesses, edges and covering areas is needed, with information on the elements retained after the renovation.
The junction between new and old material
At the repair location, the simple or milled edge joint must be identified depending on the variant, and its termination at the existing section planned. The top of the new board is the blue aluminium facing; its interaction with the retained materials must be checked. For EFYOS BLUE A, matching the core name is not sufficient confirmation of adhesion or tightness of the joint. The basis for documenting acceptance is the record of thickness and edge variant from the label. The next stage will be the waterproofing covering over the board, so the scope of the correction should be closed earlier. In the renovation documentation, it is worth distinguishing the termination of the thermal insulation at the parapet and the boundary between the old and new work.
Phasing in an occupied building
The installation of EFYOS BLUE A must be linked to the possibility of protecting the exposed section. At every stage, support for the boards with a load-distributing layer is needed, also appropriate after the old layers have been removed. The location defined as the termination of the thermal insulation at the parapet may require temporary protection during a break in work. The plan should take into account the waterproofing covering over the board, so that the next team’s date corresponds to the state of completion. Responsibility for clarifying conflicts should lie with the designer of the roof section. The polyurethane insulation will then be part of a planned renovation whose aim is to accommodate the thermal layer and preserve the correct termination of the waterproofing.
Acceptance after reinstating the layers
At acceptance, the scope covering the thermal insulation of the flat roof under the waterproofing must be compared with the scope of the agreed repair. The reference document is the parapet section with the levels of all layers, supplemented with actual dimensions. It is worth keeping the record of thickness and edge variant from the label, because once the layers are closed again the details will become invisible. The ordered PIR boards should have an identity consistent with the installed EFYOS BLUE A variant. If the problem returns, a record of how the termination of the thermal insulation at the parapet was executed will be useful. The review should not be reduced to assessing the appearance of the new surface. It must be confirmed that the thermal layer was successfully accommodated and the correct termination of the waterproofing preserved, and that the cause of the earlier defect was genuinely identified.