BauderPIR M/MF when replacing roof layers

At a glance

During the roof renovation, boards with a matt mineral fleece were partially exposed. Before supplementing the M/MF, it is worth identifying the old variant and the condition of its surface. A similar thickness of the new material does not confirm an identical thermal resistance or compatibility with the covering. The boundary of the repair should have a clearly described junction between the two parts. In a renovation, the area described as a roof with a PIR board with a mineral facing requires the old layers to be identified. The first difficult place to inspect is the area of fleece beneath the waterproofing layer. It is not worth determining the thickness of BauderPIR M/MF solely on the basis of an old drawing. The measurement should cover the thickness of the insulation being ordered and the condition of the substrate beneath the covering, taking into account changes made during earlier work.

BauderPIR board with mineral facing and exposed cream PIR core

What has to be exposed before selection

On this basis, a set of documents is produced for the specific thickness M or MF and the connection to the covering. The purpose of the assessment is to answer the question whether the existing conditions allow the correct lambda and a compatible connection to the covering to be established.

The right product and the scope of its data

For BauderPIR M/MF, the variant and thickness are needed to identify the new layer, not similarity to aluminium PIR boards. In the Polish data sheet for M, the range from 80 mm to below 120 mm has λD 0.026 W/(m·K); it should not be replaced with a constant value of 0.022. The core of this family is covered on both sides with mineral fleece. The boards have a format of 1200 × 600 mm, and M and MF are distinguished by the geometry of the edge. The documentation states a minimum of 120 kPa in the compression test and fire reaction E. Acceptance of the material should confirm a complete factory-made product with the correct surface, because the general name polyurethane insulation does not define its compatibility with the new covering.

Example versus the actual state of the renovation

Assessing the space for BauderPIR M/MF does not replace confirmation of the compatibility of the mineral facing with the chosen covering. For the height balance alone, 150 mm of available space and 50 mm required for the other layers can be assumed. 100 mm of insulation would then fit, whereas the 120 mm variant would raise the total to 170 mm. The example does not define a recommended roof or floor section; it shows the need to adjust levels when increasing the thickness. In a renovation, therefore, both the ordered dimension and the condition of the substrate must be checked, as well as the requirements of the system in contact with the fleece.

The calculation presented for BauderPIR M/MF serves to provide an initial structure for the decision. In an old building, the result must be confronted with the limitation: the condition of compatibility of the mineral facing with the chosen system. The property of the new board described as lambda dependent on the thickness of variant M does not remedy a deficit elsewhere. On site, the correct thickness range must be read from the document for the ordered variant before the final scope of work is adopted. The verification should be documented by a set of documents for the specific thickness M or MF and the connection to the covering. If it proves inconsistent with the assumption, the BauderPIR M/MF order must be adjusted before the repetitive cutting begins.

Which scope of repair is justified

One action under consideration is retaining the designed facing and selecting the required thickness. The second may be changing the entire confirmed assembly after re-comparison, depending on the result of the exploratory opening. With BauderPIR M/MF, both variants should take account of the repair location: the area of fleece beneath the waterproofing layer. Before a decision is made, the recalculation of the board with mineral facing using the lambda of the aluminium variant must be eliminated. The result of the inspection should be assessed by a specialist approving the compatibility of the insulation with the covering, who will link the repair to the remaining layers. Once agreed, a schedule of parameters is needed covering thickness, facing and edge, with information on the elements retained after the renovation.

The junction between new and old material

At the repair location, the plain profile in M or the milled profile in MF must be identified and its termination at the existing section planned. The top of the new board is a matt mineral fleece; its interaction with the retained materials must be checked. For BauderPIR M/MF, the matching of the core name is not sufficient confirmation of adhesion or tightness of the joint. The basis for documenting acceptance is the description of the fleece on both surfaces and of the correct edge profile. The next stage will be the waterproofing covering compatible with the mineral facing, so the scope of the correction should be closed beforehand. In the renovation documentation, it is worth highlighting the area of fleece beneath the waterproofing layer and the boundary between the old and new work.

Phasing in an occupied building

The installation of BauderPIR M/MF must be linked to the possibility of protecting the exposed section. At every stage, a level substrate beneath the board with undamaged fleece is required, also appropriate after removal of the old layers. The location defined as the area of fleece beneath the waterproofing layer may require temporary protection against a break in work. The plan should take account of the waterproofing covering compatible with the mineral facing, so that the timing of the next team corresponds to the state of completion. Responsibility for clarifying conflicts should lie with a specialist approving the compatibility of the insulation with the covering. The polyurethane insulation will then be part of the planned renovation, the aim of which is to establish the correct lambda and a compatible connection with the covering.

Acceptance after reinstating the layers

At acceptance, the scope covering the roof with PIR board in mineral facing must be compared with the scope of the agreed repair. The reference document is the set of documents for the specific thickness of M or MF and the connection with the covering, supplemented by the actual dimensions. It is worth retaining the description of the fleece on both surfaces and of the correct edge profile, because once the layers are closed again the details will become invisible. The ordered PIR boards should have an identity consistent with the installed BauderPIR M/MF variant. If the problem returns, a record of how the area of fleece beneath the waterproofing layer was executed will be useful. The review should not be reduced to assessing the appearance of the new surface. It must be confirmed that the correct lambda and a compatible connection with the covering were established, and that the cause of the earlier defect was genuinely identified.

7 branches. Materials closer to your project.

Izoprofil.pl map of seven branches offering sandwich panels, PIR boards and sheet metal
  • SEROCK — Dzierżenin 34 E [mapa]
  • BŁONIE — ul. Sochaczewska 138A [mapa]
  • RADOM — ul. Grobickiego 8 [mapa]
  • ŁÓDŹ — Natolin 8 [mapa]
  • OLSZTYN — Barczewo, ul. Prosta 9 [mapa]
  • WROCŁAW — ul. Jerzmanowska 10C [mapa]
  • GORZÓW WLKP. — ul. Zielona 33/34 [mapa]

Check prices and availability: +48 500 409 109

Free quote