PIR insulation
BauderPIR FA-TE in terrace renovation with a low threshold
At a glance
After the terrace surface has been removed, an uneven substrate and limited height at the doors are revealed. FA-TE should not be ordered solely on the basis of the thickness of the old material. The cross-section must be reconstructed together with the drainage. Only then can it be assessed which elements can remain and which need to be replaced. In a renovation, the scope described as insulating the terrace above a room requires an investigation of the old layers. The first difficult point to inspect is the threshold of the terrace doors and the nearby drain. It is not advisable to determine the thickness of BauderPIR FA-TE solely on the basis of an old drawing. The measurement should cover the distance between the substrate and the permissible surface level, taking into account changes made during earlier works.

What must be exposed before selection
On this basis, a terrace section at the doors is produced with the levels marked. The purpose of the survey is to answer the question whether the existing conditions allow the thermal insulation together with drainage and the terrace finishing layers to be accommodated.
The right product and the scope of its data
When ordering BauderPIR FA-TE, do not combine edge data from different documents without confirming the delivery. The British documentation describes straight edges, the Polish data sheet gives an installation dimension of 1185 × 585 mm, and the designation FA TE F refers to the variant with a rebate. The external dimension is 1200 × 600 mm. These divergent descriptions must be assigned to the correct variant before the terrace bill of quantities is produced. The board has a PIR core with aluminium facings; the data include λD 0.022 W/(m·K), CS(10/Y)120 and fire reaction E. The full product name and the confirmed profile are more accurate than general information about the delivery of polyurethane insulation.
An example versus the actual state of the renovation
The low threshold determines the permissible level of the finished surface, so begin by measuring its distance from the substrate. In the example intended only to explain the calculation, 150 mm is available, of which 50 mm is taken up by the other required layers. For BauderPIR FA-TE, 100 mm remains; choosing 120 mm would give 170 mm in total. Such a change does not fit within the assumed reserve without adjusting the levels. This is not a recommendation for the section of a specific terrace, roof or floor. The actual selection requires account to be taken of the required finish below the threshold, not just the thickness available in the range.
The calculation presented for BauderPIR FA-TE serves to provide an initial structure for the decision. In an old building, the result must be confronted with the constraint: the height limit below the threshold with the required finish. The property of the new board described as a small external format of 1200 × 600 mm does not remedy a shortfall elsewhere. On site, the height of the surface, insulation and drainage must be compared on one section before the final scope of work is adopted. The check should be documented by a terrace section at the doors with the levels marked. If it proves inconsistent with the assumption, the BauderPIR FA-TE order must be adjusted before repetitive cutting begins.
Which scope of repair is justified
One measure under consideration is changing the thickness of the thermal layer while retaining the required effect. The second may be redesigning the remaining terrace heights, depending on the result of the exploratory opening. With BauderPIR FA-TE, both variants should take account of the repair location: the patio door threshold and the nearby drain. Before deciding, the combining of data from the simple UK variant with the Polish data sheet with the smaller coverage dimension must be eliminated. The result of the inspection should be assessed by the designer of the terrace and the door connection, who will link the repair with the remaining layers. Once agreed, a description of FA-TE is needed covering the specific edge variant, with information on the elements retained after the renovation.
The junction between new and old material
At the repair location, the edge profile confirmed for the selected documentation and delivery must be identified and its termination at the existing section planned. The top of the new board is an aluminium facing with an auxiliary mesh in the variant described; its interaction with the retained materials must be checked. For BauderPIR FA-TE, matching the core name is not sufficient confirmation of adhesion or tightness of the joint. The basis for documenting acceptance is the document confirming the edge and the installation dimension of the delivery. The next stage will be finishing the terrace with waterproofing and surfacing, so the scope of the correction should be closed earlier. In the renovation documentation, it is worth highlighting the patio door threshold and the nearby drain as well as the boundary between the old and new work.
Phasing in an occupied building
The installation of BauderPIR FA-TE must be linked to the possibility of protecting the exposed section. At every stage, the distribution of load from the surfacing and its supports is required, also after removal of the old layers. The location defined as the patio door threshold and the nearby drain may require temporary protection against a break in work. The plan should take account of finishing the terrace with waterproofing and surfacing so that the next team’s date corresponds to the state of completion. Responsibility for clarifying conflicts should lie with the terrace and door connection designer. The polyurethane insulation will then be part of a planned renovation whose aim is to fit the thermal insulation together with drainage and the terrace finishing layers.
Acceptance after reinstating the layers
At acceptance, the scope covering the insulation of the terrace above the room must be compared with the scope of the agreed repair. The reference document is the terrace section at the doors with the levels marked, supplemented by the actual dimensions. It is worth keeping the document confirming the edge and the installation dimension of the delivery, because once the layers are closed again the details will become invisible. The ordered PIR boards should have an identity consistent with the installed BauderPIR FA-TE variant. If the problem returns, a record of how the patio door threshold and the nearby drain were executed will be useful. The review should not be limited to assessing the appearance of the new surface. It must be confirmed that the thermal insulation together with drainage and the terrace finishing layers could be accommodated, and that the cause of the earlier defect was genuinely identified.